Pre-feasibility study for Corpen Aike project – 4.2 GW electrolysis and 2.6 MTPA green ammonia plant, Argentina
The objective of the project was to support the client in conducting a pre-feasibility study for the implementation of a power-to-X facility, which was planned to comprise a renewable energy plant, a hydrogen generation plant, and an ammonia synthesis plant in Santa Cruz Province, Argentina. Fichtner identified the optimal project concept with the aim of minimizing the levelized cost of ammonia (LCOA) and provided a Class 5 estimate of CAPEX and OPEX for the overall project.
Our services
- Work Package 1 - Requirements & basics
- Collection and assessment of preliminary works
- Identification of the client’s strategic objectives
- Technical and operational requirements
- Work Package 2 - Preliminary design & optimization
- Techno-economic optimization using Fichtner’s H2-Optimizer
- Site selection for the main components for hydrogen and ammonia production
- Work Package 3 - Conceptual engineering
- Block flow diagram (process engineering)
- Energy & mass balance for main components
- Plant and process description
- Main utility requirement assessment
Client
- Flexen S.A., Montevideo, Uruguay